Milandhoo is growing

Island projects

What’s being built, what’s planned and what’s just opened — each with its story so far.

See every milestone on one timeline See every contract and what it cost
10being built3stopped9planned2recently completed

Being built

Under construction

Milandhoo Airport

Land reclamation finished · 4 May 2026

Next: Expected to open · 2028

See the full timeline · 13 milestones

Under construction

Milandhoo Coastal Protection

MVR 50.4M contract · Maldives Transport and Contracting Company (MTCC)

Phase 1 shown as completed · 15 February 2026

Expected 2026 (210-day contract)

See the full timeline · 9 milestones

Under construction

Milandhoo HDC Flats

Contract signed with HDC · 15 October 2025

Expected About mid-2026 (280-day contract)

See the full timeline · 3 milestones

Under construction

Milandhoo Handball Court

MVR 850,041.86 contract · Maldives Assure Supply

Handball court development · 6 August 2026

Under construction

Milandhoo Harbour

MVR 79.9M contract · MTCC

Work idle at 53% · 20 October 2026

Expected 2028, as part of the airport project

See the full timeline · 13 milestones

Under construction

Milandhoo Hospital

MVR 110.9M contract · MTCC

Groundbreaking with President Muizzu · 15 October 2025

Expected About November 2026 (600-day contract from March 2025)

See the full timeline · 8 milestones

Under construction

Milandhoo Housing Units (2022)

MVR 46M contract · Flexinc Private Limited

Still under way · October 2025

See the full timeline · 3 milestones

Building site of the Milandhoo Islamic Centre with a signboard showing the planned mosque, groundbreaking day, 15 October 2025
Under construction

Milandhoo Islamic Centre

MVR 25M contract · MTCC

Minaret and walls under way · 10 October 2026

Expected 2027

See the full timeline · 5 milestones

Under construction

Milandhoo Police Station

Groundbreaking · 15 October 2025

Asphalt paving on a Milandhoo road, Oct 2023
Under construction

Milandhoo Road Development

MVR 134.6M contract · Road Development Corporation

Phase 2 awarded · 15 October 2025

Expected 2028 (900-day contract)

See the full timeline · 18 milestones

Stopped

Planned

Recently completed

In the national budget

What the government’s investment budget (PSIP) set aside for projects on Milandhoo each year. Outlined years are the plan.

6.2M 2019 3
44.2M 2020 5
17.5M 2021 7
20.7M 2022 7
76.1M 2023 11
22.9M 2024 18
70.9M 2025 15
52.3M 2026 15

The number under each year is how many projects the budget funded that year.

Source: approved national budgets 2019–2024, “PSIP by island”, Ministry of Finance.