Milandhoo Road Development

Milandhoo Road Development

Public project

  1. Planned
  2. Under construction
  3. Open
Started
Phase 2 awarded 15 Oct 2025
Expected
2028 (900-day contract)

Phase 1 (8 roads, 6.15 km) was finished in Dec 2024. Phase 2, worth MVR 134m, includes a ring road.

About

Milandhoo’s roads are being paved and upgraded by the Road Development Corporation (RDC). Phase 1 — eight roads, 6.15 km in all — was finished in December 2024. Phase 2, awarded in October 2025 for about MVR 134 million over 900 days, adds more roads including a ring road.

#project

Key facts

Phase 1 roads
8 roads, 6.15 km, asphalted1
Phase 2 includes
A ring road2
Purpose
Ending the island's recurring flooding of roads during the monsoon3
  1. 1psmnews.mv
  2. 2presidency.gov.mv
  3. 3psmnews.mv
  1. Now
  2. 2025
  3. 15 October 2025· A year ago

    Phase 2 awarded

    The second phase of road development, including a ring road, was awarded to RDC for MVR 134 million, to be finished within 900 days.

    en.mmtv.mv
  4. 2024
  5. 15 December 2024

    Phase 1 completed

    RDC said the road project was complete and handed it to the Ministry of Construction and Infrastructure for final inspection, after several delays.

    psmnews.mv
  6. 25 April 2024

    Street lights (2024)

    The Road Development Corporation invited bids on 25 April 2024 to supply street lights for its Gdh. Gahdhoo and Sh. Milandhoo projects.

    gazette.gov.mv
  7. 2023
  8. 24 December 2023

    RDC resumes work

    The Road Development Corporation said it had restarted projects in four northern islands, including Sh. Milandhoo.

    corporatemaldives.com
  9. 22 October 2023

    Kanbarani Hingun paved

    RDC said asphalting of Kanbarani Hingun was finished, Shaheed Ali Hingun was 70% done, Huravee Magu was being paved and kerbs were going in on Ghazee Magu.

    raajje.mv
  10. 7 June 2023

    Road signs and poles

    The Road Development Corporation invited bids on 7 June 2023 to supply road signboards and poles for its Sh. Milandhoo and N. Velidhoo projects, and advertised again on 2 August and 8 August 2023.

    gazette.gov.mv
  11. 2022
  12. 18 October 2022

    Road project environmental study (2022)

    The Road Development Corporation sought a consultant on 18 October 2022 to prepare the environmental impact assessment for the Sh. Milandhoo, Adh. Maamigili and Gdh. Gahdhoo major road projects, and advertised again on 20 December 2022.

    gazette.gov.mv
  13. 2021
  14. 12 September 2021

    Asphalt materials

    The Road Development Corporation invited bids on 12 September 2021 to supply asphalt materials for its Sh. Milandhoo and Adh. Maamigili projects.

    gazette.gov.mv

Reviews

No reviews yet. Been here? Be the first to share how it was.

Rate Milandhoo Road Development

Sign in with Telegram to write a review — it keeps reviews real. One tap, no password.

Been here? Add your photos Help other visitors see what Milandhoo Road Development is like.

Photos of Milandhoo Road Development

Sign in with Telegram to share photos — one tap, no password. We’ll tell you on Telegram when they’re added.

More ways to get around