Milandhoo Coastal Protection

Milandhoo Coastal Protection

Public project

  1. Planned
  2. Under construction
  3. Open
Started
Phase 2 contract 15 Oct 2025
Expected
2026 (210-day contract)

Phase 2: 712 m revetment and 228 m groynes by MTCC for MVR 50.4m.

About

Milandhoo suffers serious beach erosion, and the government has protected its shoreline in two phases built by MTCC. The first phase, mobilised in May 2022, built a 954 m rock revetment and 115 m of groynes worth MVR 34.6 million. A second phase, signed in October 2025 for MVR 50.4 million, adds a 712 m revetment and 228 m of groynes.

#project

Key facts

Phase 1 revetment
954.43 m1
Phase 1 groyne
114.56 m (about 115 m)1
Phase 2 revetment
712 m2
Phase 2 groynes
228 m2
Implemented by
MTCC for the Ministry of Construction, Housing and Infrastructure2
  1. 1raajje.mv
  2. 2dredgingtoday.com
  1. Now
  2. 2026
  3. 15 February 2026· 8 months ago

    Phase 1 shown as completed

    MTCC's project tracker lists phase 1 (PRJ-00366) as physically completed, 100% done, in its update of 15 February 2026. The work was awarded to MTCC on 8 November 2021 and the team mobilised on 7 May 2022, for a 954.43 m revetment and 114.56 m of groynes.

    projects.mtcc.com.mv
  4. 2025
  5. 15 October 2025

    Phase 2 contract signed

    During President Muizzu's visit, MTCC signed for a 712 m revetment and 228 m of groynes worth MVR 50.4 million, to be completed within 210 days.

    en.mmtv.mv
  6. 18 July 2025

    Phase 1 still unfinished

    Residents raised concerns that phase 1 shore protection, mostly done before the 2023 change of government, was still not finished even though machinery and materials were on site.

    raajje.mv
  7. 2024
  8. January 2024

    Phase 1 at 53%

    MTCC reported 53% overall progress on phase 1 after the fifth shipment of rock boulders arrived.

    back.raajje.mv
  9. 2023
  10. 27 April 2023

    Third shipment of rock boulders

    The third shipment of rock boulders reached the site and groyne profiling was under way.

    raajje.mv
  11. 15 March 2023

    Groyne work 37% complete

    A second shipment of rock boulders reached the site, and groyne profiling was 37% complete.

    raajje.mv
  12. 2022
  13. 7 May 2022

    Construction started

    MTCC mobilised the site for a 954 m revetment and 115 m of groynes, worth about USD 2.4 million (MVR 34.6 million).

    raajje.mv
  14. 2021
  15. 8 November 2021

    Phase 1 contract signed

    MTCC was awarded Milandhoo's shore protection project for USD 2.3 million, to be finished within 200 days.

    psmnews.mv

Reviews

No reviews yet. Been here? Be the first to share how it was.

Rate Milandhoo Coastal Protection

Sign in with Telegram to write a review — it keeps reviews real. One tap, no password.

Been here? Add your photos Help other visitors see what Milandhoo Coastal Protection is like.

Photos of Milandhoo Coastal Protection

Sign in with Telegram to share photos — one tap, no password. We’ll tell you on Telegram when they’re added.

More in Community