Milandhoo Coastal Protection
Public project
- Planned
- Under construction
- Open
- Started
- Phase 2 contract 15 Oct 2025
- Expected
- 2026 (210-day contract)
Phase 2: 712 m revetment and 228 m groynes by MTCC for MVR 50.4m.
About
Milandhoo suffers serious beach erosion, and the government has protected its shoreline in two phases built by MTCC. The first phase, mobilised in May 2022, built a 954 m rock revetment and 115 m of groynes worth MVR 34.6 million. A second phase, signed in October 2025 for MVR 50.4 million, adds a 712 m revetment and 228 m of groynes.
Key facts
- Phase 1 revetment
- 954.43 m1
- Phase 1 groyne
- 114.56 m (about 115 m)1
- Phase 2 revetment
- 712 m2
- Phase 2 groynes
- 228 m2
- Implemented by
- MTCC for the Ministry of Construction, Housing and Infrastructure2
Timeline
Island timeline- Now
- 2026
-
15 February 2026· 8 months ago
Phase 1 shown as completed
MTCC's project tracker lists phase 1 (PRJ-00366) as physically completed, 100% done, in its update of 15 February 2026. The work was awarded to MTCC on 8 November 2021 and the team mobilised on 7 May 2022, for a 954.43 m revetment and 114.56 m of groynes.
projects.mtcc.com.mv - 2025
-
15 October 2025
Phase 2 contract signed
During President Muizzu's visit, MTCC signed for a 712 m revetment and 228 m of groynes worth MVR 50.4 million, to be completed within 210 days.
en.mmtv.mv -
18 July 2025
Phase 1 still unfinished
Residents raised concerns that phase 1 shore protection, mostly done before the 2023 change of government, was still not finished even though machinery and materials were on site.
raajje.mv - 2024
-
January 2024
Phase 1 at 53%
MTCC reported 53% overall progress on phase 1 after the fifth shipment of rock boulders arrived.
back.raajje.mv - 2023
-
27 April 2023
Third shipment of rock boulders
The third shipment of rock boulders reached the site and groyne profiling was under way.
raajje.mv -
15 March 2023
Groyne work 37% complete
A second shipment of rock boulders reached the site, and groyne profiling was 37% complete.
raajje.mv - 2022
-
7 May 2022
Construction started
MTCC mobilised the site for a 954 m revetment and 115 m of groynes, worth about USD 2.4 million (MVR 34.6 million).
raajje.mv - 2021
-
8 November 2021
Phase 1 contract signed
MTCC was awarded Milandhoo's shore protection project for USD 2.3 million, to be finished within 200 days.
psmnews.mv