Fenaka's office on Heenaa Goalhi handles electricity, water and related utility services for the island — the place to go for connections, bills and service questions. The three-storey building, designed for 54 staff, opened on 1 August 2023. It's a couple of minutes' walk from Milandhoo School and Sarudhaaru Maizaan.
Key facts
- Storeys
- 31
- Staff capacity
- 541
Timeline
Island timeline- Now
- 2023
-
1 August 2023· 3 years ago
Opened by President Solih
President Ibrahim Mohamed Solih opened the new three-storey Fenaka office, built for 54 staff, during his Shaviyani tour.
raajje.mv - 2020
-
24 February 2020
Contract signed
Fenaka contracted Vehicon Builders to build its Milandhoo office for USD 622,242, to be finished within 305 days.
psmnews.mv -
14 January 2020
New Fenaka office building
Fenaka re-tendered the building of a new office in Sh. Milandhoo on 14 January 2020, because its earlier notice (FNK-I/IUL/2019/260) drew too little response.
gazette.gov.mv - 2019
-
24 November 2019
New office tendered
Fenaka invited bids to build a new office building in Milandhoo, to its drawings and bill of quantities. Gazette notice FNK-I/IUL/2019/260.
gazette.gov.mv