Public project
- Planned
- Under construction
- Open
- Started
- Work began 16 May 2023
- Expected
- 2028, as part of the airport project
MTCC harbour upgrade (MVR 79.9m contract) from 2023; MTCC’s tracker shows it idle at 53% (20 Oct 2026), against a planned finish of January 2025. The harbour is being relocated and replaced by a new, larger one under the airport project.
About
Milandhoo's harbour sits on the island's southern shore and is where boats and launches come and go. MTCC began a major harbour development project here in May 2023, including a new basin, a 583 m breakwater, a quay wall, two bridges and a 130 m jetty. The government has also announced that, under the Milandhoo Airport plans, a new harbour will replace the existing one, so the layout may change in coming years.
360° view
Key facts
- New basin dredging
- 72,938 m³ (70,400 m³ in the first scope)1
- Maintenance dredging
- 17,900 m³1
- Channel dredging
- 8,400 m³1
- Breakwater
- 583 m1
- Quay wall
- 316 m1
- Revetment
- 93 m1
- Groyne
- 25 m1
- Jetty
- 130 m × 2 m1
- Bridges
- Two (20 m × 3 m and 54 m × 3 m)2
- Harbour paving
- 3,863 m²1
- Future
- To be replaced by a new, larger harbour under the MACL airport agreement3
Timeline
Island timeline- Now
- 2026
-
20 October 2026· Recently
Work idle at 53%
MTCC's project tracker lists the harbour upgrade (PRJ-00544) as idle, 53% complete, in its update of 20 October 2026. It was awarded to MTCC on 8 December 2022 with completion planned for 5 January 2025. The work covers 99,238 cbm of dredging, a 316 m quay wall, 701 m of rock shore protection, a 130 m jetty, a 74 m bridge and 3,863 sqm of paving.
projects.mtcc.com.mv -
5 May 2026
Temporary relocation under way
Once reclamation finished, the harbour area was reported to be moving temporarily to make way for airport construction, with provision for it in the airport design.
psmnews.mv - 2025
-
15 October 2025
Relocation announced
President Muizzu said the existing harbour would be relocated and a larger new harbour built as part of the MACL airport project, all within 30 months.
presidency.gov.mv -
14 July 2025
Council says works are slow
The council's deputy president said the harbour upgrade was the only project still under way and that work was going very slowly, with long gaps between working days.
raajje.mv - 2023
-
23 October 2023
Quay wall blocks complete
Quay wall block installation was finished and concrete work was under way. Dredging of the new basin was 26% complete.
raajje.mv -
23 October 2023
New basin dredging 26% complete
MTCC said quay wall block placement was finished, quay wall concrete work was under way and basin dredging was 26% done.
raajje.mv -
20 September 2023
Quay wall blocks 53% placed
MTCC delivered its fourth shipment of concrete blocks, and quay wall block installation reached 53%. The project was valued at MVR 76.44 million.
raajje.mv -
31 August 2023
Second shipment of quay wall blocks
MTCC delivered a second shipment of concrete blocks for the quay wall.
raajje.mv